This Mill/resurface project includes minor improvements to drainage, sidewalk and guardrail with a duration of 150 days.

Traffic Impacts

There are no traffic impacts at this time.

Note: All information is preliminary and subject to change without notice.

Project Overview

Project Number 441540-1
Work Type Resurfacing
Status UNDER CONSTRUCTION
Project Length 5.510 miles
Estimated Completion Fall 2021
Project Manager Shannon Harris

Affected Areas

Roads Sr 30 (us 98) From E
Counties Franklin