Project Overview

Project Number 437365-1
Work Type Resurfacing
Status CONST.COMPLETE
Project Limits
Apalachee Parkway (S.R. 20 / US 27) to 7th Avenue and the intersection of Apalachee Parkway and Magnolia Drive
Project Length 1.201 miles
Estimated Completion Spring 2020
Est. Construction Cost $5.2 Million
Project Manager Shannon Harris

Project Documents

Affected Areas

Roads SR 265
Counties Leon