SR 289 (9th Ave) over Carpenter Creek Bridge

FDOT office in Chipley
Project photo
SR 289 (9th Avenue)

Project Details

The Florida Department of Transportation (FDOT) began a $4.3 million construction project to replace the existing bridge culvert on North Ninth Avenue (State Road 289) over Capenters Creek. The work also includes resurfacing North Ninth Avenue between Royce Street and Bayou Boulevard and a portion of Carpenters Creek Drive. Additional improvements will include drainage upgrades: new curb and gutter: lighting system improvements: and new signage, pavement markings, guardrail, and sidewalks.

Traffic Impacts

RECENT PROGRESS: Bridge is open to four lanes of traffic, two in each direction. Drivers will continue to encounter intermittent and alternating lane closures as crews paint thermoplastic pavement markings

Note: All information is preliminary and subject to change without notice.

Project Overview

Project Number 437178-1
Work Type Bridge Replacement
Status Construction
Project Limits
south of Carpenters Creek Dr to north of Royce Street
Project Length 0.152 miles
Estimated Completion Winter 2022
Est. Construction Cost $4.27M
Project Manager Georgina Acierto-Kent

Project Documents

Affected Areas

Roads SR-289/N 9th Ave
Counties Escambia
Cities Pensacola

Public Meetings

Contact

Georgina Acierto-Kent
(850) 981-2804

Data Current as of 06/20/2022