The Florida Department of Transportation (FDOT) will begin work in March 2022 to mill and resurface a 3.1-mile segment of U.S. 29 (Pensacola Boulevard) from Brent Lane (State Road 296) to north of the I-10 in Escambia County.Additional work will include curb ramp, and sidewalk improvements, new signage and pavement markings, and enhanced signalization.

Traffic Impacts

RECENT UPDATES: Drivers may encounter alternating lane closures Sunday through Thursdays from 9 p.m. to 6 a.m for paving operations. Contractor is grading at sidewalks, placing handrails and utility work.

Note: All information is preliminary and subject to change without notice.

Project Overview

Project Number 434677-1
Work Type Resurfacing
Status Construction
Project Limits
SR 95 (US 29) from SR 296 (Brent Ln) to south of I-10
Project Length 3.100 miles
Estimated Completion Spring 2023
Est. Construction Cost $6.30M
Project Manager Georgina Acierto-Kent

Project Documents

Affected Areas

Roads US-29/SR-95/Pensacola Blvd
Counties Escambia
Cities Pensacola

Public Meetings

Contact

Georgina Acierto-Kent
(850) 981-2804

Data Current as of 04/14/2022