Project Details

<p style="margin-top:0in;margin-right:0in;margin-bottom:0in;

margin-left:.5in;text-align:justify;line-height:normal;font-size:11.0pt;font-family:Calibri,sans-serif;">Contractor continues planned removal replacement of existing

concrete, installation of new sidewalk, and pedestrian signal upgrades. Milling

Resurfacing with structural asphalt has been performed in R3 L3

throughout project limits and will continue.

Traffic Impacts

Drivers may encounter alternating lane closures Sunday through Thursdays from 9 p.m. to 6 a.m for paving operations

Note: All information is preliminary and subject to change without notice.

Project Overview

Project Number 434677-1
Work Type Resurfacing
Status Construction
Project Limits
SR 95 (US 29) from SR 296 (Brent Ln) to south of I-10
Project Length 3.100 miles
Estimated Completion Winter 2023
Est. Construction Cost $6.30M
Project Manager Georgina AciertoKent

Project Documents

Affected Areas

Roads US-29/SR-95/Pensacola Blvd
Counties Escambia
Cities Pensacola

Public Meetings

Contact

Georgina AciertoKent
(850) 981-2804

Data Current as of 04/14/2022