The intent of this project is to resurface existing travel lanes,auxiliary lanes, and paved shoulders.
Additional Improvements include:
*Additional curb and gutter with 6 foot sidewalk from Park Place Apartments to Hyde Park Road
*Signalization and ADA improvements at Summit Boulevard and Langley Avenue intersections
*Drainage improvements
*Safety improvements
Note: All information is preliminary and subject to change without notice.
Project Overview
Project Number
426935-2
Work Type
Resurfacing
Status
Design
Project Limits
from south of Hyde Park Road to south of SR 8 (I-10)
Project Length
4.824 miles
Project Manager
Sandra Lamb
Project Documents
Affected Areas
Roads
US-90/SR-10A/Scenic Hwy, I-10/SR-8, Hyde Park Rd
Counties
Escambia
Cities
Pensacola
Public Meetings
Contact