SR 397 (John Sims Parkway) over Toms Bayou

FDOT office in Chipley
Project photo

Project Details

The construction project will replace the northbound bridge (570055) over Toms Bayou. The new structure will include two 12-foot travel lanes, an eight-foot outside shoulder, and a five-foot sidewalk. The southbound span will be widened to accommodate an eight-foot outside shoulder and five-foot sidewalk.

Traffic Impacts

Drivers will encounter periodic nighttime lane closures and traffic shifts. During Phase 2 of construction, three lanes of traffic will be maintained on the bridge. The inside lane will become a "reversible lane" to allow two southbound lanes (toward Eglin AFB) during morning peak travel times and two northbound (away from Eglin AFB) lanes during the afternoon/evening.

Note: All information is preliminary and subject to change without notice.

Project Overview

Project Number 406194-3
Work Type Bridge Replacement
Status UNDER CONSTRUCTION
Project Limits
Toms Bayou Bridge Project
Project Length 0.129 miles
Estimated Completion Winter 2020
Est. Construction Cost 8.5
Project Manager Joseph Waters

Project Documents

Affected Areas

Roads SR 397 (John Sims Prky)
Counties Okaloosa
Cities Niceville

Public Meetings

Contact

Joseph Waters
850-836-5748

Data current as of 1/8/2019