Project Details

FDOT is conducting a Project Development and Environmental (PD&E) Study (220635-2, 220635-4) to assess present features, consider community needs and impacts, and develop possible improvements for SR 20 from Cat Mar Road in Okaloosa County to east of SR 79 in Washington County.

The intent of the study is to address capacity and safety and improve regional mobility.

The project has been divided into three segments:

Segment 1 – Cat Mar Road in Okaloosa County to King Road in Walton County;

Segment 2 – King Road to CR 3280 (Black Creek Boulevard) in Walton County

Segment 3 – CR 3280 (Black Creek Boulevard) to east of SR 79 in Washington County.

Based on the findings of the previously completed Feasibility Study, capacity improvements to SR 20 within the overall project limits are only justified in Segment 2 (King Road to Black Creek Boulevard).

Public Engagement Opportunities

* Public Hearing: April 2021

* Virtual (online) Project Update: May 2020

* Project Kickoff Newsletter: April 2019

Additional information will be provided as it becomes available.

Note: All information is preliminary and subject to change without notice.

Project Overview

Project Number 220635-2
Work Type PD&E Study
Status PRE-CONST.UNDERWAY
Project Limits
from the Okaloosa County line to Washington County line
Project Length 31.988 miles
Estimated Completion Summer 2021
Project Manager Tori White

Project Documents

Affected Areas

Roads SR 20
Counties Washington, Walton, Okaloosa
Cities Freeport, Bruce, Ebro

Public Meetings

Contact

Tori White
850-330-1455

Data current as of 04/29/2021