Northwest Florida Roads

Skip to main content

US 29 from I-10 to north of Nine Mile Road

FDOT office in Chipley
Project photo
captions on photos

Project Details

Crews continue to construct median curb and place sod along US 29 and 9 Mile Road, traffic wall

under the new Bridge and new roadway construction on 9 mile Rd. Frontage Road on northwest quadrant is open in its final configuration

And In the next two weeks they are scheduled to complete and open all Ramps at Hwy 29 & 9 Mile Rd in its final configuration.

Traffic Impacts

Alternating lane closures on US29 (southbound and northbound) and lane shift on 9 Mile Rd (eastbound and westbound) when needed by the contractor.

Note: All information is preliminary and subject to change without notice. Anticipated final acceptance is August 15, 2021

Project Overview

Project Number 218603-1
Work Type Add Lanes & Reconstruct
Status UNDER CONSTRUCTION
Project Limits
from SR 8 (I-10) to north of SR 10 (US 90A) Nine Mile Road
Project Length 2.632 miles
Estimated Completion Fall 2021
Est. Construction Cost $48.9 M
Project Manager Georgina Acierto-Kent

Project Documents

Affected Areas

Roads SR 95, US 29
Counties Escambia
Cities Ensley, Brent

Public Meetings

Contact

Georgina Acierto-Kent
850-981-3000

Data current as of 08/05/2021